I am preparing my shop floor to receive a Kiwa mill ( ~7000lbs). Where it will need to be placed will straddle 2 concrete slabs with an expansion joint in the middle. One of the slabs is true and level, while the other has a 2 deg downslope -- about 1.5 inch of drop over 36 inches.
Should I pour some self leveling concrete into that space (about 36" x 60"), or should I just shim the machine and call it good? The spindle and electronics box will be over the spot where I would have to pour/shim.
Advice?
Thanks!
-Ben
Should I pour some self leveling concrete into that space (about 36" x 60"), or should I just shim the machine and call it good? The spindle and electronics box will be over the spot where I would have to pour/shim.
Advice?
Thanks!
-Ben