matt_isserstedt
Diamond
- Joined
- Dec 15, 2003
- Location
- suburbs of Ann Arbor, MI, USA
Thanks all for helping me thru my myriad of concrete questions...
...latest burning question revolves around moving the concrete from a truck to be placed in the slab.
A couple of specifics, 25' x 40' size, only accessible on 2 sides due to existing buildings. There will be a stem-wall sticking 8" higher than the finished floor, around the full perimeter with a cut-down for a 9 foot garage door. Expected pour of 18-20 cu yards for 5-6" slab. Field of #4 rebar tied 16" on center throughout the slab, on 2" chairs.
Calling various ready mix places they all seem to agree on the cost for a pumper truck being in the close neighborhood of $1k.
The concrete truck chute would seem to have a range of around 15 feet but that is a long way to move seeing that only half of the area is directly accessible.
I can rent something like a Whiteman (its a brand name...) gasoline powered concrete buggy around $120-150 per day which seems like a lot of savings.
The functional sticking point is traversing the field of rebar with the buggy. It seems like if I layer some sheets of plywood for support of the load (estimating 3/4 yard @ 3000 lbs + buggy weight) and then suspend the ply above the rebar grid with something like a group of 2x6 or 2x10 blocks laid flat between the spaces of the grid, I could accomplish it via having a buggy driver dedicated to running back and forth.
I also don't have a good feel for how much concrete is "wasted" in priming the pump truck..the booms are like 30 meters/100 feet so it seems like there would be some extra that would have to be ordered.
So I seek the sage advice of the membership...spend the extra for the pump truck, use the plan above, or something completely different? Thanks in advance.
...latest burning question revolves around moving the concrete from a truck to be placed in the slab.
A couple of specifics, 25' x 40' size, only accessible on 2 sides due to existing buildings. There will be a stem-wall sticking 8" higher than the finished floor, around the full perimeter with a cut-down for a 9 foot garage door. Expected pour of 18-20 cu yards for 5-6" slab. Field of #4 rebar tied 16" on center throughout the slab, on 2" chairs.
Calling various ready mix places they all seem to agree on the cost for a pumper truck being in the close neighborhood of $1k.
The concrete truck chute would seem to have a range of around 15 feet but that is a long way to move seeing that only half of the area is directly accessible.
I can rent something like a Whiteman (its a brand name...) gasoline powered concrete buggy around $120-150 per day which seems like a lot of savings.
The functional sticking point is traversing the field of rebar with the buggy. It seems like if I layer some sheets of plywood for support of the load (estimating 3/4 yard @ 3000 lbs + buggy weight) and then suspend the ply above the rebar grid with something like a group of 2x6 or 2x10 blocks laid flat between the spaces of the grid, I could accomplish it via having a buggy driver dedicated to running back and forth.
I also don't have a good feel for how much concrete is "wasted" in priming the pump truck..the booms are like 30 meters/100 feet so it seems like there would be some extra that would have to be ordered.
So I seek the sage advice of the membership...spend the extra for the pump truck, use the plan above, or something completely different? Thanks in advance.